2017 Water & Sewer Rehab Projects

Schedule 1:  South 24th Street West Waterline Replacement

Project Overview:

See the attached exhibit for an overview of the upcoming work areas and general project status.  Construction on 24th Street West during the week beginning July 31 will be occurring from Mall Drive to Phyllis Lane.  New water line installation will resume south of Pueblo Drive, including both mainline pipe underneath the center turn lane and lateral pipelines across the west lanes.  Paving is scheduled to occur during the daytime on Thursday & Friday, August 3 & 4, from Mall Drive to Pueblo Drive with only one lane of travel open in each direction on 24th Street West in the immediate vicinity of the work.  All other work this week will occur at night between the hours of 7:00 PM – 7:00 AM, Sunday night through Friday morning.  With the exception of Thursday & Friday, typical daytime traffic conditions will allow for two lanes of traffic in each direction.  Business access will be maintained throughout the project duration, although there may be times when only one of multiple entrances to each business is able to remain open during working hours.  All reasonable efforts will be made to minimize inconveniences to businesses and to general traffic flow.

August 4, 2017 Update:

See the attached exhibit for an overview of the upcoming work areas and general project status. Construction on 24th Street West during the week beginning August 13 will be occurring from Pueblo Drive to Monad Road.  New water line installation will be completed at the intersection of Monad Road and 24th Street West early in the week.  The east leg of that intersection will continue to be closed to traffic during pipeline testing and asphalt restoration, with a detour in place.  The detour will route thru-traffic to King Avenue West via 20th Street West and 24th Street West.  Work this week will occur during both daytime and nighttime hours on various days.  Paving may occur during the daytime from Pueblo Drive to Monad Road on Thursday & Friday, August 17 & 18.  During working hours, traffic will be limited to one lane of travel in each direction on 24th Street West in the immediate vicinity of the work, and during non-working hours there will be two lanes open in each direction.  Business access will be maintained throughout the project duration, although there may be times when only one of multiple entrances to each business is able to remain open during working hours.  All reasonable efforts will be made to minimize inconveniences to businesses and to general traffic flow.

  • Water line replacement on 24th Street West from Central Avenue to Monad Road
  • Estimated start of construction:  June 5th
  • Waterline is in center of the street
  • Primarily night work

Schedule 2


August 14, 2017 Update:

See the attached “Schedule 2 Weekly Update” maps for an overview of the active work areas and general project status for Schedules 2A, 2B, and 2C.  

Schedule 2A:  32nd Street Waterline Replacement

Work this week will consist of the contractor beginning replacement of the water main and services in North 32nd Street between Avenue C and Avenue E.  The contractor will also continue to set up temporary water setup ahead of construction.  Traffic control will consist of a closure to North 32nd Street from Avenue C to Avenue E.  Access for area residents and businesses will be maintained throughout the project duration. 

  • Water line replacement on North 32nd Street from 9th Avenue North to 12th Avenue North
  • Work in front of McKinley school to be completed before school starts
  • Commuter impact at Parkhill/N. 32nd/11th Ave. North intersection

Schedule 2B:  Rose Park Area Sewer Replacement

Work this week will consist of the contractor continuing to replace sewer main in the alley generally bounded between Avenues B and C from 20th Street West to 19th Street West.  Construction crews will be in alleys replacing manholes and sewer main, and will restore the surface once construction of the sewer in the alley is complete.  In addition to alley closures, traffic control will consist of a closure in 20th Street West.  A lane shift will also occur in 19th Street West.  Access for area residents and businesses will be maintained throughout the project duration.  Alley and road restoration will continue for the areas completed between Avenues B and D from 17th Street West to 19th Street West.


  • Sewer Replacement in alleys
    • Between Ave. C and Ave. D from 17th Street West to 21st Street West
    • Between Ave. B and Ave. C from 17th Street West to BBWA Canal (Approx. 25th St. West)
  • Work primarily in alleys and local streets, except for tie-ins and crossing of major streets
  • Timing of major street crossings dependent on contractors schedule
  • Work in 17th Street West at the alley between Ave C and Ave D will require full closure of 17th for a short period
  • Other work in 17th, 19th, and 24th Streets West will maintain two way traffic

Schedule 2C:  Miles/Howard/Cook from 26th – 28th Street West Sewer Replacement

Work this week will consist of the contractor continuing to replace sewer main in the alley south of Cook Avenue from 26th Street West to 28th Street West.  Construction crews will be in alleys replacing manholes and sewer main, and will restore the surface once construction of the sewer in the alley is complete.  In addition to alley closures, traffic control will consist of closures to 26th Street West and 27th Street as they continue construction to the west.  Access for area residents and businesses will be maintained throughout the project duration.  Alley and road restoration will continue for the areas completed from 26th Street West to 28th Street West.                      


  • Sewer Replacement in alleys between 26th Street West and 28th Street West
    • Between Miles Avenue and Howard Avenue
    • Between Howard Avenue and Cook Avenue
    • Alley south of Cook Avenue
  • Work primarily in alleys and local streets, except for tie-ins and crossing of major streets

Schedule 3:  6th Avenue North Water and Sewer Replacement

August 14, 2017 Update:

This week the contractor installed water main from the intersection of 6th Avenue North/Grand Avenue/North 32nd Street to the 6th Avenue North/North 31st Street intersection.  There will be miscellaneous work occurring in the 6th Avenue North/Grand Avenue/North 32nd Street over the next couple of weeks including making water main connections, cleanup and paving, but a majority of the work is completed in this busy intersection! 

For the week of August 14, 2017, the contractor will continue installing water main east through the 6th Avenue North/North 31st Street intersection towards North 30th Street.  Testing will also be performed on the new water main installed through the 6th Avenue North/Grand Avenue/North 32nd Street intersection to the 6th Avenue North/North 31st Street intersection.  Traffic control will consist of maintaining two lanes of traffic on 6th Avenue North from North 30th to North 32nd Street.  There will still be some detours setup for the remaining work in the intersection of 6th Avenue North/Grand Avenue/North 32nd Street.  

Access to businesses and residents will be maintained.

The construction work zones are highlighted on the Schedule 3 Project Map.    
  • Sewer and Waterline Replacement from N. 27th Street to Grand Avenue
  • Commuter impact/Traffic Control
    • Will maintain 2 lanes of traffic on 6th Avenue
    • N. 32nd and Division will have short duration closures
    • Grand Avenue will be constricted to one lane in each direction
  • May include some night work

TRAFFIC/ACCESS

 

Thank you for your patience and consideration as the Contractor performs work in your area.
Program History  
The City of Billings Water and Sanitary Sewer Replacement Projects were initiated in 1979 as part of an overall strategy to keep the City’s water distribution system and sanitary sewer collection system in the best possible overall condition.With only a few exceptions, the City has replaced water and sewer mains each year since 1979.

Indicators of Replacement Needs
A number of indicators are utilized to identify areas of the system needing replacement and generally include:
  • System capacity analysis
  • Water main break history
  • Sanitary sewer back-up complaints
  • Sanitary sewer root intrusion maintenance activity
  • Sanitary sewer video analysis
  • Public Works Department street improvement projects

Scheduling



Generally, the replacement projects scheduled in any given year are first prioritized based on coordination with plans the Engineering Division has to improve City streets. City resources are best utilized and the public best served when marginal water and sanitary sewer systems in streets scheduled for improvement are replaced along with the street improvements; this way, newer streets are not cut for utility replacement long into the foreseeable future.

Secondly, an attempt is made to concentrate water and sewer replacement projects in a limited number of geographical areas each project year.By replacing systems in only a few areas each construction season, the City does not burden it’s customers in that area with construction-related inconveniences for multiple years within a reasonable time span.Also, the City is able to obtain more competitive bid prices on the work performed if the projects are not scattered throughout the City.

The Distribution and Collection Division prioritizes portions of the system for replacement on a rolling five year schedule; this schedule must remain flexible and project priorities change frequently based on changing public needs from year to year. The amount of work actually performed each year is based on available budget.Recent annual project budgets have been on the order of about $3.5 million each for water and sanitary sewer replacement.In the last five years, the lineal footage of water and sewer replacements have been on the order of 7,500 to 12,500 feet each for water and sewer.