Grand Avenue (8th - 12th)

Overview
The City of Billings has been working on widening Grand Avenue from 8th Street West to 12th Street West. The project includes replacement of:
  • Water main
  • Sanitary sewer
  • Storm drain
  • Widening to five lanes
  • Installation of seven-foot wide sidewalk on both sides of the street
  • Reconstruction of the street
The City of Billings had anticipated that construction of Grand Avenue would start Spring of 2004. However, due to complications involved in the right of way acquisitions and budget shortfalls, the Grand Avenue Project was delayed.

Construction Delays
Throughout the year of 2006, the City of Billings has continued to work with the affected property owners regarding right of way acquisitions.