2019 Water & Sewer Rehab Projects

Schedule 1:  North 27th Street West Water Main Replacement


Project Overview:


The 'North 27th Street Water Main Replacement Project' includes the replacement of over 5,000 feet of water mains on North 27th Street between 6th Avenue North and Rimrock Road. The current 16-inch cast iron water line, originally installed in 1945, has deteriorated with age and experiences frequent breaks. This project will replace the pipeline along with all valves and hydrants along the corridor. This project will allow the City of Billings Public Works Department to better serve their water customers, reduce annual system maintenance costs, convey water more efficiently to other areas of the water distribution system, and sustain a safe and reliable infrastructure. Construction will start in February 2019 and the total construction time will be approximately 4 to 5 months. The project will be constructed by COP Construction. DOWL is the City's engineering consultant that prepared the design and will be overseeing construction. . Project updates will generally be provided on a weekly basis during construction by email and on the City’s website.

June 29, 2019 Update:

See the attached project exhibit for an overview of the upcoming work areas and general project status. See the attached project exhibit for an overview of the upcoming work areas and general project status. Water main installation on North 27th Street has been completed. The remaining work for the week starting July 1 includes a small amount of asphalt patching and other miscellaneous work items. Additional lanes of North 27th Street will continue to be opened up to traffic as this work is completed. If necessary, only minor cleanup and punch list work is expected after next week. This will be the final email and website update for this project.

Schedule 2:  Montana Avenue Sewer Main Replacement


September 16 - 20 Update:


See the attached “Weekly Update” map for an overview of the active work areas and general project status.  

Construction will consist of the contractor continuing sewer main replacement on the north half of 1st Avenue North generally bound between North 17th Street and North 21th Street. Once the sewer installation is complete, the contractor will move to North 16th Street and Montana Avenue to install new storm drain inlets. A subcontractor will also be installing concrete curbing, approaches, and sidewalk at various locations. The paving subcontractor will begin prepping and paving North 18th Street and 1st Avenue North. North 18th Street will be closed and detoured to North 17th Street for east bound traffic and North 19th Street for west bound traffic to facilitate construction. Lane reductions will occur in 1st Avenue North during the sanitary sewer installation and paving process. Local side street closures may occur during surface restoration and sewer installation along Montana Avenue and 1st Avenue North. Access for area businesses will be maintained throughout the project duration; however, parking restrictions may occur when construction is directly adjacent to the businesses.
                                    

   

Schedule 3:  Southside Triangle Waterline Replacement Project


September 9 - 13 Update:

See the attached project exhibits (Exhibit 1, Exhibit 2) for an overview of the anticipated work scheduled for the week of 09/09 - 09/13. Water main installation will continue along 4th Avenue S. between S. 27th Street and S. 29th Street. The second water main crew will continue work on S. 36th Street between 2nd Avenue S. and 4th Avenue S. Both locations will include the replacement of fire hydrants, re-connection of all services and the replacement of lead services from the new main line to curb stop. 

Paving is anticipated for S. 32nd Street from 7th Avenue S. to 4th Avenue S.

Please be aware of traffic control surrounding the affected streets as traffic will be routed around the construction area. All reasonable efforts will be made to minimize inconveniences to area residents through the project duration.   

TRAFFIC/ACCESS

 

Thank you for your patience and consideration as the Contractor performs work in your area.

close carousel
close carousel
close carousel
close carousel
close carousel
close carousel
close carousel
close carousel
close carousel
close carousel
close carousel
close carousel
close carousel
close carousel
close carousel
close carousel
close carousel
close carousel
close carousel
close carousel
close carousel
close carousel
close carousel
close carousel
close carousel
close carousel
close carousel
close carousel
close carousel
close carousel
close carousel
close carousel
close carousel
close carousel
close carousel
close carousel
close carousel
close carousel
close carousel
close carousel
close carousel
close carousel
close carousel
close carousel
close carousel
close carousel
close carousel
close carousel
close carousel
close carousel
close carousel
close carousel
close carousel
close carousel
close carousel
close carousel
close carousel
close carousel
close carousel
close carousel
close carousel
close carousel
close carousel
close carousel
close carousel