Monad & Daniel Traffic Signal Improvement Project

September 30 - October 04 Update:

Underground utilities are complete and the intersection has been paved. Last week, the contractor started work on the traffic signal installation which included signal foundations, conduit, the and the signal controller base. They closed Daniel St for two days to install utility valve and manhole collars, and there are not any expected closures for the remainder of the project. Knife River will work to install sidewalk at the intersection this week with final striping scheduled for the end of the week/early next week.