Monad & Daniel Traffic Signal Improvement Project

September 9 - 13 Update:

All of the new water line has been installed, however tie-ins will still need to be made to connect the newly installed main to the existing main outside the intersection. The contractor will continue to work on storm drain and general road work required for the widening. Monad Rd is planned to be open to through traffic by 9/17 pending any weather related setbacks. Daniel will remain closed to complete road improvements in that portion of the intersection. We ask that through traffic continue to use the signed detour for both Monad and Daniel and appreciate your patience while the intersection is constructed.